CSX Transportation will begin a maintenance project Monday, February 2 on eight selected at-grade crossings along parts of the CSX Fitzgerald subdivision, the company announced last week.
Work is expected to take two weeks, tentatively ending Friday, February 13 weather permitting. Crossings will be closed between two and five days depending on the type of maintenance they are to receive, CSX said.
Be advised the estimated closure time frames are merely the best approximation CSX can provide at this time. The dates are highly subject to change with or without notice simply due to unforeseen circumstances that can occur once the work begins.
With the one way in/out crossings, CSX will work as diligently as possible to have those accessible within a 24 hours (or less).
Following is a list of the crossings ticketed for maintenance with their estimated closure dates.
• Garlington Avenue: On-around February 2;
• Dewitt Street: Onaround February 2;
• McKinley Road: Onaround February 3;
• Fred Voight Road: On-around February 3;
• Crestwood Road: Onaround February 4;
• JF Herndon Road: On-around February 5;
• Maudes Lane: Onaround February 6;
• Marvin Rouse Road (1 Way In/Out): On-around February 9.